Nordex N-131
6 windturbines
Waardpolder

Services

Windfarm Waardpolder

Windfarm Waardpolder

The Waardpolder gained 6 new turbines in cooperation with WP Energiek and Topwind. The turbine of choice were the Nordex N-131 turbines and they were build in 2020.

The maximum production is 20 MW. The turbines are not able to produce their maximum, due the size of the cable. The total electricity production is enough for 24.000 households.